Project Schedule

Anticipated Construction Schedule

The construction schedule for the Methuen Rotary Construction Project and associated activities are outlined in detail below. Please note: some stages are concurrent for a period of time.

Total construction duration – 4 years
Stage 1 – June 2014 to April 2015

  • Tree, shrub and building removal
  • Existing I-93 median barrier and paving removed to accommodate traffic shifts
  • New underground Verizon duct banks installed
  • Riverside Drive bridge widened and Columbia gas work started under bridge
  • Begin construction of new I-93 southbound on- and off-ramps
  • Sound walls built on east side of I-93
  • Lowell Street east of the rotary reconstructed to Forest Street
  • Haverhill Street reconstructed to Burnham Road
  • Wetlands mitigation at former Loosigian Farms

Stage 2A – January 2015 to August 2015

  • Begin construction of new I-93 bridge over center of rotary
  • Continue I-93 southbound on- and off-ramps construction

Stage 2B – August 2015 to December 2015

  • Continue construction of I-93 bridge over center of rotary
  • Continue I-93 southbound on- and off-ramps construction
  • North Lowell Street (Route 113 west of rotary) widened to Albert Street
  • Utilities installed and Branch Street paved west of rotary

Stage 2C – December 2015 to July 2016

  • Complete I-93 bridge over center of rotary
  • I-93 southbound off-ramp completed
  • Temporary north and southbound on- and off-ramps constructed
  • Complete I-93 southbound on-ramp
  • Bolduc Street, Route 110 and North Lowell Street to west of Albert Street reconstructed

Stage 3A – June 2016 to November 2016

  • Complete new I-93 southbound on-ramp
  • Begin demolition of existing rotary bridges
  • Complete stormwater detention basins
  • Begin new I-93 northbound off-ramp

Stage 3B – November 2016 to April 2017

  • Continue demolition of existing rotary bridges

Stage 3C – April 2017 to August 2017

  • Continue demolition of existing rotary bridges
  • Complete new I-93 northbound off-ramp

Stage 4 – August 2017 to June 2018

  • Remove temporary I-93 median paving
  • Install median concrete barrier
  • Complete final I-93 paving and striping

Construction completion – now Spring 2018!